Detailed Explanation of Tea Machine Installation Steps and Precautions
At present, the processing units for famous and high-quality tea in tea-producing areas are composed of individual machines. During installation, pay attention to the following:
1. Install the unit according to the tea-making process. For newly built factories, the number of machines, operating space and leaf-spreading area should be taken into account. For the general production line arrangement of machinery, the horizontal direction is arranged in vertical rows.
2. Select the knife switch and wire diameter according to the power load of the processing machinery. Protective measures should be taken for the passage lines, and a monitoring lamp should be installed on each phase of the distribution board to prevent operation with a broken phase.
3. Pay attention to the running direction of the machinery. If it is opposite to the specified direction, swapping any two of the three phases will change the direction.
4. The smoke pipe should be installed at the specified height, avoiding 90-degree bends, so as not to affect the combustion performance of the machinery.